A. A permanent storm water control plan (PSWCP) for each project subject to the provisions of this chapter shall be submitted and accepted by the department prior to issuance of a site development permit.

B. The PSWCP must be developed by a certified professional in erosion and sediment control or a professional engineer registered and licensed in the state of Alaska and shall include the following items as set forth in the standards of this chapter:

1. The name and contact information of the site owner;

2. Project site plan;

3. BMP selection narrative;

4. BMP sizing and design information; and

5. BMP operation and maintenance schedule.

C. Payment of the plan review fee must accompany each PSWCP submittal.

D. The department shall conduct a review of the PSWCP and accept the PSWCP, accept the PSWCP with conditions, or reject the PSWCP in writing based on its conformance with the standards set forth in this chapter.

E. Any applicant may petition the department for reconsideration of a decision regarding a PSWCP submittal within 30 days of the decision. Any such reconsideration request must be accompanied by the original submittal documents and the specific reason for requesting reconsideration. The department will notify the applicant within seven days if reconsideration of the decision is granted. Reconsideration decisions are final decisions appealable to the superior court in accordance with the rules of appellate procedure.

F. No person shall commence with construction of a project regulated by this chapter without an accepted PSWCP. (Ord. 2009-27 § 5, 2009. 2004 Code § 21.50.020.)